MEP Cost Forecast at Completion: Separate Incurred Cost from Open Commitments

An MEP package has used only 473,000 cost units against a 900,000 budget, yet its current completion forecast is 938,000. The apparent unused budget does not establish how much work the balance can buy. Equipment still to arrive, unfinished subcontract work, remaining labor and site support must all be forecast before the package can be described as under budget.
The practical question is: what cost has already been incurred, and what additional cost is now expected to finish the defined scope? This article develops an internal cost-control example, using fictional cost units (CU). It does not determine accounting recognition, customer revenue, payment entitlement or a selling price.
Build three non-overlapping cost buckets
The US Department of Energy’s EVM training defines estimate at completion as actual cost to date plus the estimate to complete. It also calls for the remaining estimate to reflect performance, corrective actions and anticipated problems. Subtracting actual costs from an old budget merely calculates unused budget; it does not independently estimate the remaining work.
Incurred cost: cost already recognized against this package under the team’s consistent reporting basis, including supported accruals for received goods or completed work where appropriate.
Remaining committed cost: the portion of current orders and subcontract commitments that relates to cost not already included in incurred cost.
Remaining uncommitted cost: forecast completion work not covered by those remaining commitments, such as future direct labor, missing procurement scope or time-related site costs.
For this model, EAC = incurred cost + remaining committed cost + remaining uncommitted cost. Define the buckets before importing software columns. A system’s “committed cost” may mean the whole approved order, rather than its remaining portion. Adding that whole amount to actual costs would count the completed portion twice.
Procore’s own forecasting guidance illustrates why labels require checking: its standard Forecast to Complete column covers potential costs not already captured in other live cost columns. It also distinguishes individual allowances from recurring, duration-based costs. Map exported fields to your model instead of assuming every system uses the same definition.
Freeze the cut-off and reconcile one equipment order
Assume one unchanged package, one reporting date and a consistent CU basis. The 900,000 CU comparison budget and the forecast cover the same installation scope and site-support boundary. Exclude taxes, financing, company overhead, profit and a separate risk reserve. Any assessment of those excluded amounts needs its own explicit line or companion report.
The current approved equipment order is 350,000 CU. Supplier invoices already included in package cost total 190,000 CU. A further 20,000 CU of received equipment is supported by a delivery record and included as an accrual. Incurred equipment cost is therefore 210,000 CU, leaving 350,000 − 210,000 = 140,000 CU of the order for future cost.
An order report based only on invoices may show 160,000 CU outstanding. Adding that figure to the 210,000 CU incurred total would overstate equipment cost by the 20,000 CU accrual. Reconcile order lines to receipts, invoices and accrual references. Payment status does not settle the classification: an unpaid invoice can already be fully included in incurred cost.
Rebuild the remaining scope by cost driver
The following inputs are invented for teaching. The equipment order excludes a separately forecast freight item. The ductwork subcontract is current at 220,000 CU; a further 12,000 CU of expected completion work sits outside that commitment. Treat that amount as a cost forecast, without assuming anything about approval or recovery from another party.
Direct labor: 126,000 CU incurred; no remaining purchase-order commitment; 4,500 remaining person-hours × 32 CU/person-hour = 144,000 CU uncommitted. Forecast total: 270,000 CU.
Equipment: 210,000 CU incurred; 140,000 CU remaining commitment; 8,000 CU forecast freight outside the order. Forecast total: 358,000 CU.
Ductwork subcontract: 95,000 CU incurred; 220,000 − 95,000 = 125,000 CU remaining commitment; 12,000 CU separately forecast completion work. Forecast total: 232,000 CU.
Site support: 42,000 CU incurred; no remaining purchase-order commitment; 8 remaining weeks × 4,500 CU/week = 36,000 CU uncommitted. Forecast total: 78,000 CU.
Totals are 473,000 CU incurred, 265,000 CU remaining committed and 200,000 CU remaining uncommitted. The estimate to complete is 465,000 CU. EAC = 473,000 + 265,000 + 200,000 = 938,000 CU. Compared with the 900,000 CU budget, the forecast overrun is 38,000 CU, or 4.22% of budget.

Original fixed-scope teaching example. CU means fictional cost units. Remaining commitments exclude costs already incurred; no separate risk reserve is included.
The remaining labor estimate needs physical work quantities, productivity assumptions and the future crew cost. Here, the 32 CU rate applies to remaining person-hours, not crew-hours. A three-person crew working one hour contributes three person-hours. Do not reuse a historical hourly average if the future labor mix, burden or approved working pattern has changed.
Test that routine transactions do not manufacture a saving
Suppose the supplier submits the invoice for the 20,000 CU already accrued. Replacing the accrual with that invoice leaves incurred cost at 473,000 CU, provided the invoice matches the estimate. The remaining commitment and EAC also stay unchanged. Any genuine invoice-versus-accrual difference needs its own explained adjustment.
Next, 50,000 CU of equipment previously forecast within the remaining order is received and recognized. Incurred cost rises to 523,000 CU; remaining committed cost falls to 215,000 CU. Their sum remains 738,000 CU, and total EAC remains 938,000 CU. Progress has moved cost between buckets without changing the final expectation.
Similarly, awarding the already forecast 8,000 CU freight item transfers 8,000 CU from uncommitted to committed remaining cost. It creates no forecast saving by itself. These simple transaction tests expose spreadsheets that retain a full allowance after the corresponding order has been raised.
Explain forecast movements with changed evidence
Now consider a separate delay scenario: two additional site-support weeks cost 9,000 CU, while the revised work plan requires another 400 person-hours at 32 CU, adding 12,800 CU. The scenario increases EAC by 21,800 CU to 959,800 CU. It does not follow that every two-week delay has this cost; the added hours and weekly support scope must be justified for the actual job.
Keep that scenario separate until the team decides which assumptions belong in its current forecast. Do not add the same known labor effect both to remaining hours and to a general risk allowance. Preserve the original comparison budget and log the cause of each forecast movement so a revised estimate cannot silently erase an overrun.
Make the next review actionable
Give each cost row a scope owner, cut-off date, source record and remaining-quantity basis.
Reconcile current order values and changes, then remove the portion already present in incurred cost.
Walk the unfinished installation, testing and closeout scope with the delivery team to find missing remaining work.
Record what changed since the previous forecast, what remains uncertain and which decision is needed next.
Nexora’s paid Business and Job Cost Tracker HVAC can help organize the estimated-versus-actual material and technician-hour records that feed a cost review. Its product description includes burdened labor and job-cost comparisons. Maintain the open-commitment and completion forecast described here as a separately reconciled schedule; do not assume those forecasting functions are built into the workbook. Align reporting treatment with your finance team before using the result for formal accounts.