MEP Delivery Lots: Check Peak Storage and Pallet-Days Before Choosing a Batch Size

Oct 21
5 min read
Illustration of organized pipe bundles and building-services materials in warehouse storage bays.

Illustrative engineering scene. The worked calculation below uses explicit example inputs.


Two suppliers can offer the same equipment scope and still create different site costs through their delivery arrangements. One proposes a single bulk shipment. Another will release smaller lots against the installation sequence. Comparing freight charges alone misses the storage peak, the number of days material waits and the extra handling created when the site cannot receive the shipment.


Start with a daily physical stock model. It exposes infeasible options before a commercial comparison makes them look attractive. Transport for London and CLOCS guidance identifies delivery management as a way to coordinate bookings and site arrivals. The example below develops an original estimating model around that operational problem; it is not a claim that one batch size suits every project.



1. Define a storage unit that reflects the delivery


Assume 40 identical packaged fan coil units, each occupying one unstacked pallet position. The installation team can remove four units from storage each working day. The work takes ten consecutive working days in the simplified model. Deliveries arrive before the day’s issues, and accepted units are available for installation that morning. There is no opening stock.


The site logistics team has confirmed 12 usable pallet positions for this package, after allowing for access and other reservations. That is an input to the estimate, not an instruction to infer storage capacity from gross floor area. Real equipment may have unequal package sizes, weight restrictions or environmental requirements. Manufacturer instructions must govern handling and protection. Carrier’s 42EP instructions, for example, call for checking shipment condition and retaining packaging until close to installation.



Model two quantities each day: stock immediately after receipt, which governs peak space, and closing stock, which governs the chosen storage-charge convention. The example assumes a daily charge based on closing stock. An actual warehouse might charge by occupied day, week, minimum period or reserved bay; substitute the quoted rule. The ten modeled days are consecutive installation and chargeable days, with no intervening non-working days. Add weekend and holiday holding days wherever the actual calendar and charging rule require them.


Stock after receipt = previous closing stock + today’s delivery.


Closing stock = stock after receipt − today’s issues.


Peak requirement = largest stock-after-receipt value.


Pallet-days = sum of closing stock × days held at that level.


Three same-scale step charts show morning pallet positions over ten days. Bulk peaks at 40 above the 12-position capacity, 12-unit lots reach 12, and 8-unit lots peak at 8.

Morning receipt peaks, not closing stock, determine whether site capacity is exceeded. Closing-stock pallet-days are 180, 36 and 20 for the three plans.


2. Reject the bulk plan on capacity


Plan A delivers all 40 units on day 1. The closing stock is 36, 32, 28, 24, 20, 16, 12, 8, 4 and zero units over days 1–10. That totals 180 pallet-days. Its peak is 40 positions immediately after receipt, despite the closing-stock average being only 18.


The plan exceeds the available 12 positions. It cannot be described as the cheapest feasible direct-delivery plan. An off-site store could make bulk purchasing possible, but that creates a different option with receiving, storage, transfer deliveries and additional handling to measure. Do not hide that option’s costs inside the original single-delivery assumption.


3. Compare two feasible staged plans


Plan B receives 12 units on days 1, 4 and 7, then four units on day 10. Closing stock follows 8, 4, zero, repeated for the first three cycles, followed by zero. Peak storage is 12 positions, and there are four deliveries.


Plan B pallet-days = (8 + 4 + 0) × 3 + 0 = 36.


Plan B total receipts = 12 + 12 + 12 + 4 = 40 units.


Plan C receives eight units on days 1, 3, 5, 7 and 9. Closing stock alternates between four and zero. Peak storage is eight positions. There are five deliveries, leaving four positions of baseline capacity headroom on receipt days.


Plan C pallet-days = (4 + 0) × 5 = 20.


Plan C total receipts = 8 × 5 = 40 units.


Additional deliveries versus Plan B = 1.


Reduction in closing-stock storage = 36 − 20 = 16 pallet-days.


A same-day receipt followed by installation still needs unloading and staging space. Closing-stock charges may be zero for that day, but the physical peak is not. Where the receiving bay is separate from the store, model transfer capacity and timing as well; a daily total can conceal a congested morning.


4. Compare only the costs that change


For illustration only, use 150 cost units per delivery and three cost units per closing-stock pallet-day. These invented rates are not supplier quotations or local market benchmarks. Assume the equipment cost, unloading effort per unit, installation effort and all other costs are identical. No discounts, financing effects, taxes or contractual penalties are included.


Plan A, before its capacity failure: 1 × 150 + 180 × 3 = 690 cost units.


Plan B: 4 × 150 + 36 × 3 = 708 cost units.


Plan C: 5 × 150 + 20 × 3 = 810 cost units.


Plan C premium over Plan B = 150 − 16 × 3 = 102 cost units.


Plan B has the lower modeled cost among the feasible baseline plans. Plan C buys additional space headroom at an illustrative premium of 102 cost units. If only these two cost drivers vary, their break-even daily storage rate is 150 ÷ 16 = 9.375 cost units per pallet-day. Above that rate, Plan C becomes cheaper; below it, Plan B remains cheaper on this limited basis.


Before using the comparison, distinguish an incremental charge from a fixed site cost. If the same reserved store is paid for regardless of occupancy, fewer pallet-days may release useful space without reducing an invoice. Conversely, an additional delivery can trigger a minimum unloading call-out even when the equipment quantity is unchanged.


5. Stress-test one missed installation day


Now assume installation stops on day 3, then resumes at four units per day with no catch-up. Keep the original delivery bookings for the test. In Plan B, four units remain at the end of day 3. The day-4 receipt of 12 raises stock to 16 before installation, exceeding the 12-position limit. The baseline fit had no capacity reserve at that point.


Plan C enters day 3 with zero closing stock from day 2 and receives eight units. None are installed that day, leaving eight. Day 4 reduces that to four; the day-5 receipt raises stock to 12. Subsequent receipt-day peaks remain at or below 12, and the final four units are installed on day 11. This particular pause fits spatially, but still extends the installation sequence. It does not establish resilience to late deliveries or multiple lost days.


6. Turn the estimate into a release rule


  • Confirm package dimensions, stackability, protection requirements and the net space actually allocated to the package.

  • Obtain written delivery-lot terms, minimum shipment charges, release notice periods and any storage or rebooking charges.

  • Maintain a receipt-and-issue ledger by equipment type and location, not only one project-wide total.

  • Before each release, check closing stock plus the proposed receipt against available capacity and the next workfront’s readiness.

  • Update the model with actual receipts, accepted quantities and installation issues. Keep rejected or quarantined items visible because they still occupy space.


The decision is a documented trade-off between freight, storage and operational room to respond. A plan that fits only when every daily assumption succeeds deserves different treatment from one with headroom. The daily inventory model makes that distinction visible before the order is released.



Continue the calculation review




Sources and calculation basis


Primary references checked on 21 October 2026. The worked examples and diagrams are original illustrative calculations, not manufacturer selections or project approvals. Apply the stated limitations and the requirements governing the actual project.