Supply Fan Run Proof: Separate Command, Drive Status and Delivered Airflow

Illustrative comfort AHU commissioning; not a photograph of a Nexora project.
A building automation system (BAS) can show a supply fan as running while the air handler still delivers too little air. A start command shows intent, a drive signal reports its configured state, and an airflow switch proves a condition at its own sensing points. None measures how much air reaches the occupied space. Test those signals separately before accepting a comfort air-handling unit (AHU).
Give each point one job
Trend the effective fan command, variable-frequency drive (VFD) run feedback, air-proving input and any independent measured airflow on a common clock. Label the source of each signal. A point copied from the command is not independent feedback. VFD feedback can report a running drive without detecting a failed belt or a blocked duct. Confirm what the selected hardware actually reports and distinguish a stale or invalid value from a genuine off signal.
List the pressure tap locations and the switch's on and off thresholds. The AHU Selection & Fault Diagnosis Handbook gives a broader commissioning and fault-review workflow. Siemens’ airflow-switch instructions illustrate how the application depends on the model and sensing arrangement. A pressure differential across a fan can exceed the proving threshold without demonstrating adequate airflow. Use the approved sequence, sensor instructions and commissioning evidence at the lowest intended operating duty to check how the proof behaves.
Check the alarm and then check the air
An ASHRAE example for a general exhaust fan compares command with status for an alarm. In the fictional comfort AHU below, the example sequence allows 30 s after the effective command for both drive feedback and air proof. The drive confirms at 8 s. In one witnessed normal run, proof closes at 22 s; it has 8 s to spare in this example. In an approved failed-proof simulation, the drive again confirms at 8 s, but the proof stays open through 30 s. The expected result is a failed-proof alarm at the timeout, not a successful start. Check the specified alarm, operator indication, fallback and clearing behavior; the 30 s value is not an industry default.

Fictional comfort-AHU startup checks; actual timeouts and responses are project-specific.
A proving-switch differential is not a velocity-pressure measurement. For an independent traverse, the Pitot velocity calculator converts one valid local total-minus-static pressure reading to local speed, not whole-duct airflow.
Now consider a different steady test in which both binary signals are true. The supply duct is 0.50 m × 0.40 m. An independent traverse gives representative mean velocities of 4.5, 4.0, 3.5 and 4.0 m/s for four equal-area zones. The area-weighted mean is 4.0 m/s, so the duct airflow is 0.20 m² × 4.0 m/s = 0.80 m³/s. Against the example design target of 1.00 m³/s, the measured supply flow is 20% low. The proof test passed, but the airflow did not meet the example duty. This supply-duct measurement does not establish outdoor or individual zone airflow.
Close the exception with evidence
Save the point map, annotated startup and fault trends, sensor references and measured airflow with the applicable operating mode. If proof passes but airflow is low, confirm the test basis and investigate run speed, filters, damper position or other restrictions before changing thresholds. Use the four-zone airflow calculator to check the area arithmetic once you have representative equal-area zone means. Four convenient duct readings do not replace the specified traverse procedure. Also verify that unexpected feedback with the fan commanded off is handled as specified, and remove all authorized test overrides at closeout.
Use approved test methods and qualified personnel. Do not bypass protective interlocks or apply this example to smoke control, process ventilation or a safety circuit. For the separate duty and measurement review, see Nexora’s fan commissioning and TAB guide.